OAR 340-095-0090(4)(a) Cost Estimates.
A detailed written estimate of the third-party costs in current
dollars (as calculated using a discount rate equal to the current yield
of a 5-year U.S. Treasury Note as published in the Federal Reserve’s
H.15 (519) Selected Interest Rates for the week in which the calculation
is done), prepared by a Registered Professional Engineer, of:
(A) Closing the non-municipal land disposal site;
(B) Providing post-closure care, including installing, operating and
maintaining any environmental control system required on the
non-municipal land disposal site;
(C) Performing required corrective action activities; and
(D) Complying with any other requirement the Department may impose as a
condition of issuing a closure permit, closing the site, maintaining a
closed facility, or implementing corrective action
Click on the following link to the Federal Reserve Site to find the
5-year yield for this week: