|

|
McCormick and Baxter Superfund Cleanup Site
Environmental Cleanup Site Information Number (ECSI):
74
County:
Multnomah
City:
Portland
Region: Northwest
Contact Information
Project Manager:
Kevin Parrett
Phone: 503-229-6748
E-mail:
Site Summary
The McCormick and Baxter site is located on the northeast shore of the
Willamette River in north Portland. The site includes 41 acres of land
and 23 acres of sediments beneath the Willamette River.
McCormick and Baxter Creosoting Company operated between 1944 and 1991,
treating wood products with creosote, pentachlorophenol, and inorganic
(arsenic, copper, chromium, and zinc) preservative solutions.
Historically, process wastewaters were discharged directly to the
Willamette River, and other process wastes were dumped in several areas
of the site. Significant concentrations of wood-treating chemicals have
been found in soil and groundwater at the site and in river sediments
adjacent to the site.
Current Documents and Supporting Information
General Information
- Fact Sheet PDF
- Photo Gallery (5MB PDF file)
- First Five-Year Review PDF
A "Five-Year Review" was conducted in 2001 of the McCormick and Baxter
Site to determine whether the selected remedy, as described in the 1996
ROD, is providing protection to human health and the environment.
Superfund, the federal cleanup law, requires that these reviews be
conducted every five years. The next Five-Year Review will be conducted
in 2006.
- City of Portland Site Reuse Assessment Report
This report presents the results of a site reuse assessment conducted
between February 2000 and June 2001 by the City of Portland Bureau of
Planning under a grant by EPA. In developing reuse recommendations the
City analyzed the site’s redevelopment potential and engaged
stakeholders and the interested public in learning about, proposing and
jointly considering what uses would best fit the site. The City’s
findings were presented in a final report dated June 2001 which has been
endorsed by the Portland City Council. In conducting the assessment, the
City developed a list of reuse criteria that would need to be balanced
in order to arrive at the most feasible land reuse, such as minimizing
traffic impacts, ensuring adequacy of infrastructure, being compatible
with cleanup remedies, serving an identified market or community needs
and being consistent with the City of Portland Comprehensive Plan. Using
these criteria, the City developed, presented and discussed a variety of
reuse ideas and conceptual site plans. Four reuse scenarios were further
studied and reviewed at public open houses: an open space demonstration
site, recreational use, industrial use and mixed use (residential,
commercial and university facilities). Project consultants prepared
market feasibility and traffic analysis reports for these four
scenarios. The City concluded that the site is best suited for
recreational use.
Reports
- Surface Water Sampling Work Plan and Reports
- Preliminary Closeout Report PDF
This Preliminary Close Out Report (PCOR) documents that the Oregon
Department of Environmental Quality (DEQ) has completed all construction
activities for the McCormick & Baxter Creosote Company Superfund Site,
in accordance with the EPA guidance, Close Out Procedures for National
Priorities List Sites (OSWER Directive 9320.2-09A-P, January 2000). EPA
conducted a pre-final inspection on September 26, 2005, and determined
that DEQ constructed the remedies in accordance with remedial design
(RD) plans and specifications. The PCOR summarizes removal and
remedial actions; the pre-final, final and joint inspections;
institutional controls; redevelopment potential; activities and schedule
for site completion; remedial costs and five-year ROD reviews.
- Organoclay Laboratory Study Report - September 2005 PDF
The University of Texas at Austin, under contract by DEQ, performed a
series of experiments to assess the sorption capacity, permeability,
swelling characteristics, leachability and strength of two selected
organoclays when exposed to nonaqueous phase liquids (NAPLs) from the
McCormick and Baxter Creosote Site. This work will be used to determine
the long-term monitoring and maintenance requirements of the organoclay
cap placed over several creosote seeps along the Willamette River beach
front.
- Barrier Wall Construction Summary Report - April 2004
This Remedial Action Construction Summary Report summarizes construction
activities and provides the as-built (record drawings) for the combined
sheet pile and soil-bentonite barrier wall. The barrier wall was
constructed to fully encompass 17.8 acres of NAPL impacted groundwater
and the main contaminant source areas at the site, including the former
Tank Farm Area (TFA) and Former Waste Disposal Area (FWDA). The total
length of the wall is 3,792 linear feet and the depth varies from
approximately 45 feet below ground surface (bgs) to 80 feet bgs to
account for differences in the topography and soil profile at the site.
Approximately 1,440 feet of the barrier wall along the bank of the
Willamette River were constructed using steel sheet piles. Installation
methods involved a panel-driving technique, which consisted of setting
and partially driving six to eight sheet pile pairs (a panel).
Approximately 2,355 linear feet of soil-bentonite barrier wall were
installed to depths of up to 80 feet bgs to the side and upgradient of
the primary contaminant source areas. The excavated trench was held open
using a slurry mix of bentonite and water, which was later displaced by
the denser soil-bentonite mixture. The mixing operation occurred
concurrently with excavation within the wall’s perimeter. The soil-bentonite
mixture consisted of soil excavated from the trench, slurry from the
trench, imported clayey soil, and dry bentonite. The mixing and
placement were accomplished by an excavator and bulldozer.
Record of Decision
- Amended Record of Decision PDF
The Amended ROD changes a component of the selected remedial action for
contaminated soil. The original soil remedy in the 1996 ROD called for
excavation and on-site biological treatment of contaminated soils. After
the ROD was signed, DEQ initiated the detailed design of the selected
soil remedy, including additional soil sampling. Based on the data
gathered during the sampling, DEQ determined that dioxin contamination
of soils was more widespread than previously reported. Accordingly, DEQ
and EPA have selected an alternative remedy for contaminated soil at the
McCormick & Baxter site.
- Record of Decision
The Record of Decision (ROD) addresses contaminated soil, groundwater,
and sediment at the McCormick and Baxter Creosoting Company, Portland
Plant site (McCormick & Baxter or site) located in Portland, Oregon. The
selected remedy is a series of remedial actions that address the
principal threats at the site by treating the most highly contaminated
soil, extracting nonaqueous phase liquid (NAPL) and treating
contaminated groundwater, and capping the most highly contaminated
sediment. These are considered to be the final actions needed to control
the release of contaminants and reduce the risks to human health,
welfare, and the environment from the site.
- Explanation of Significant Difference
PDF
The Explanation of Significant Difference describes the rationale for
implementing the contingency groundwater remedy specified in the 1996
Record of Decision for the McCormick & Baxter Site. This contingency
groundwater remedy is a subsurface, impermeable barrier wall. The
barrier wall will encircle 16 acres of highly contaminated groundwater
and extend to a depth of up to 80 feet below ground surface. The barrier
wall design should be completed by the end of September 2002 with
construction anticipated in late 2002 or early 2003.
Feasibility Study
The Feasibility Study (FS) was completed in September 1995 for the
McCormick & Baxter Superfund Site. The FS was revised from an earlier
version prepared under State of Oregon guidelines prior to the 1994
Superfund declaration. The revised FS incorporates both Federal and
State guidelines. The FS develops remedial action alternatives and
evaluates these alternatives against remedy selection factors and
protectiveness of human health and the environment. The revised FS
proposes the most feasible alternatives which meet the remedial action
objectives for protecting human health and the environment. The FS is
the basis for the Record of Decision. The complete study is available on
CD, please contact Deborah Curtis at
503-229-6361.
Remedial Investigation
The Remedial Investigation (RI) was completed in September 1992 for the
McCormick & Baxter Superfund Site. The RI provides information on site
conditions, environmental contamination, and risks associated with the
site. The RI is the basis for the Feasibility Study. The complete RI is
available on CD, please contact Deborah Curtis at
503-229-6361.
|